PART 1 - GENERAL
| 1.1 |
Provide
all labor, equipment and materials to furnish and install prefabricated
portable steel building(s) where shown on the drawings. |
| 1.2 |
Related
work specified elsewhere |
| 1.2.1 |
Electrical
service supply and connection. |
| 1.2.2 |
Site/foundation
work. |
| 1.2.3 |
Unloading,
placement, installation and anchoring. |
| 1.2.4 |
Plumbing
& piping (if required). |
| 1.3 |
References
|
| 1.3.1 |
Prefabricated
building manufacturer shall provide the locations and owners
of 3 similar buildings that have been in service more than three
years so that the architect can inspect on site and obtain a
statement from the owners on the quality of workmanship (fit
and finish). |
| 1.4 |
Submittals
|
| 1.4.1 |
Upon award
of order, manufacturer shall prepare and submit shop drawings
for each different building required for this project. Drawings
shall include elevations, section, floor plan, electric schedule,
service entrance locations, and anchor clip detail. |
| 1.4.2 |
Color
charts illustrating available colors and patterns for specified
finishes shall be submitted to owner for prompt selections.
|
| 1.5 |
Quality
assurance |
| 1.5.1 |
Structures
shall be the product of a manufacturer with a minimum of 20
years-documented experience in the design and fabrication of
portable steel buildings. |
| 1.5.2 |
The approved
manufacturer is Par-Kut International, Inc., 40961 Production
Drive, Harrison Township, Michigan, 48045, Phone (586) 468-2947,
Fax (586) 463-6059, website: www.parkut.com, email: sales@parkut.com.
|
| 1.5.3 |
Manufacturer
shall maintain and furnish proof of maintenance of quality assurance
program with regularly scheduled independent third party testing.
Production process will include 5-stage, 35-step inspection.
|
| 1.5.4 |
Prefabricated
buildings by manufacturers other than the one approved shall
submit sufficient data to enable approval to be given. As a
minimum: design drawings and/or calculations, applicable certifications,
catalog information, and color samples showing equal range of
variety. |
| 1.5.5 |
A request
for substitution must include a list of three or more projects
in satisfactory service for not less than three years that use
products identical to those being proposed for substitution.
For each project, provide name, address, and telephone number
of the A/E firm, the contractor and the owner. Requests for
substitution after bids have been submitted will not be considered.
|
| 1.5.6 |
Electrical
devices factory installed within the prefabricated building
shall be UL listed. Factory installed wiring system shall bear
UL Classification label certifying compliance with the current
NFPA's National Electrical Code |
| 1.5.7 |
Adherence
to applicable portions of state and local building codes is
the responsibility of the installing contractor. Building manufacturer
shall not be responsible for permits, special engineering calculations,
or architectural type drawings unless otherwise notified in
writing three weeks prior to release of bid document. |
| 1.5.8 |
Design
loads: Live Loads: Floor 50 PSF, roof 50 PSF, wind 100 MPH.
|
PART 2 -
PRODUCTS
| 2.1 |
Short
form specification: Pre-assembled booth unit(s) shall be Model
__________ (Model is determined by length first then width.
i.e. 6' x 8' booth is model 86) as manufactured by Par-Kut International,
Inc. |
| 2.2 |
Structure:
Prefabricated steel building shall be single unit welded steel
construction with 14-gauge galvannealed steel panels and tubing
on the exterior and 18-gauge galvannealed steel interior panels.
Building to be shipped completely assembled. All welded joints
ground smooth. Aluminum or fiberglass construction not acceptable.
|
| 2.3 |
Base and
floor: Base height shall be 4 inches for outside use. Floor
shall be 12-gauge galvanized steel, 4-way tread plate. Four
1/4" steel angle iron anchor clips with pre-drilled holes are
provided to secure building. Anchors provided by installer shall
be galvanized or stainless steel. |
| 2.4 |
Door(s)
shall be top suspended sliding aluminum type, fully weather
stripped. Include manufacturer's standard lock, glazing and
hardware. |
| 2.5 |
Windows:
Shall be clear anodized aluminum construction and include glazing
and all hardware as required. Provide sliding windows as shown
on drawings for ventilation and/or transaction purposes. Include
insect screens in ventilation windows. |
| 2.6 |
Glazing:
All windows and doors shall contain clear tempered safety glass,
1/8" minimum thickness |
| 2.7 |
Finish:
All steel surfaces shall be painted with rust inhibitive epoxy
primer. All exposed interior and exterior steel surfaces shall
be painted with one finish coat of industrial acrylic epoxy.
Choice of single color of paint as selected by owner from manufacturer's
standards. |
| 2.8 |
Canopy:
Shall be 14-gauge minimum galvannealed steel and standard overhang
shall extend 3" beyond the walls. Standard fascia height shall
be 6". |
| 2.9 |
Roof:
Provide lifting ring(s) welded in roof for onsite lifting of
unit. Roof surface shall be 14-gauge galvannealed steel sheet.
Roof seams shall be continuously welded, caulked and weatherproofed.
Roof shall drain to downspout(s). |
| 2.10 |
Insulation:
Walls shall be insulated with 2" rigid fiberglass board, R=10.
Roof structure fully insulated, R=17.4. |
| 2.11 |
Work counter:
One 14-gauge painted steel counter across width of booth. Include
one 16" wide steel storage drawer. Counter shall be welded in
place. Include one electrical cord access hole install in counter
above receptacle. |
| 2.12 |
Electrical:
Unit shall be delivered complete with all wiring required for
fluorescent light with lamp, switch, one 110V duplex outlet,
heater, a 100A 12-circuit load center with branch circuit breakers
and 100A main breaker. All wiring copper No. 12 minimum, enclosed
in EMT. All fittings, wiring devices and fixtures UL listed.
Ready for site connection. Three wire 240/120V single-phase
service required. |
| 2.13 |
Heater:
Electrical wall heater shall be fan-forced type including integral
thermostat. Minimum heater size shall be 120V/1500W. (Specify
optional 208/240V units for larger buildings and cold climates.)
|
| 2.14 |
Optional
features: Provide items available from manufacturer's optional
equipment list at direction of owner/architect to best meet
site requirements. |
PART 3 -
EXECUTION
| 3.1 |
General:
Install prefabricated buildings on flat and level concrete pad
in accordance with the manufacturer's recommendations and placement
drawings. Position units over utility stub-ups, verify building
is level and anchor. |
Par-Kut